Canidelo Apartments

Canidelo Apartments

Canidelo Apartments is a beachfront ground-up development. The location is zoned as commercial and services, suitable for mixed commercial and hotel development. The goal is to develop serviced apartment for sale and lease back.

  • Address:

    Lote 19, Avenida Beira Mar, V.N de Gaia

  • Total construction area:

    11,232 sqm

  • Estimated Investment Timeline:

    03.2023 – 12.2026
    (45 months)

  • Report issue:

    #5

  • Date of Issue:

    310-06-2024

  • Next Issue:

    30-09-2024

1. Project Updates

  • Two official information requests were submitted (PIP), one for a single volume building and another for two volumes building.
    • The one volume PIP request for appreciation suspension was approved in order for the allotment change to be submitted and approved.
    • The two volumes PIP will be rejected due to the volumes proposed will not match with the allotment change now submitted.
    • New allotment change was submitted to city hall to change the zoning to add tourism use and also increase the number of units, and is under appreciation. The process requires approval of the Culture Department, Tourism of Portugal department and public discussions. 
    • Legal Advert was installed on the plot.
    • Currently we have approval from the Culture Department, we have resubmitted the documentation after correction to their comments
    • After Tourism of Portugal approval that we expect to be at the end of July 2024 the public notice will be issued for discussion and 30 days after we should have the approved allotment change, by beginning September 2024.
    • The PIP shall be changed according to the allotment change and therefore by the end of september 2024/ Beginning of October we shall get the approved PIP.
  • After the process of allotment change is completed, we could move forward with project execution ready for construction. The comunicação prévia shall be issued with all projects in order to start construction.
  • Adriano Pimenta Arquitectos, Lda conducted the concept phase and preliminary study for one volume building, which resulted in 80 units of tourism apartments. Plans of the current study are shared in the photos area. The plans shared include:
    • 80 Units with 80 parking spaces
    • Mainly Typologies of 1 bedroom units and also some 2 bedroom units
    • Indoor Pool, gym and reception areas.
  • Fire Safety consultant and Structural Engineer consultant, were also involved in this stage of the preliminary design in order to stabilize layouts and solutions and incorporate the requirements needed.
  • Tourism expertise Consultant also is involved in order to set out and include all the requirements needed for these type of projects (Tourism Apartments)
  • Multiprojectus from Garcia Garcia will be hired as the engineering team for the project. Multiprojectus will be responsible for the execution of projects, and construction supervision and also be involved in the concept and licensing phases. The total fee agreed upon was €220,000. (not awarded)

2. Financial Updates

  • For the 1st quarter of 2024 doesn’t exist major updates on the financial plan.

I Capital Structure & Profit Forecast

On March 2023, the fund acquired the asset holding company (Sparkling Joy, Lda) via a combination of share purchase and shareholder’s loan (as of September, 2023 the total equity injected is €2.25M:

  • Capital: 525,000 euros
  • Shareholder’s loan: 1,725,000 euros

After reassessment of the project's business plan we are presenting the following scenarios for equity requirements and respective profits:

  • Scenario A:
    • Total common equity required of €4.0M which will be used to support land acquisition costs and 100% of project's soft costs;
    • In this scenario would be required an additional capital injection of €2.8M. This additional cash could be provided through common equity injections or other alternative instruments such as preferred equity or debt.
    • At this stage, we do not have full visibility over the alternatives that could be applied to this project which means that the estimated profit for this scenario will need to be reviewed according to the financing costs.
    • According to the assumptions (including interest rate update) and limitations above identified we are pointing for a return of equity of 53.4%
  • Scenario B:
    • In this situation common equity will be used to support land acquisition costs, soft costs, 15% of hard costs and furniture expenses. In this scenario we have assumed an assumption where the bank loan for construction will not exceed 85% of the total amount.
    • Besides the construction loan, we are not expecting any other instruments of debt. Common equity required to this would be higher (€7.0M), however this will significantly change the return of equity to 31.9%. 

Capital Structure & Financing
  • Total Estimated Project Cost

    19,226,569.00€

  • Total Capital Invested

    2,250,000.00 €

  • Debt Financing

    11,233,340.00 €

  • Construction Loan

    11.233.340,00 €

  • Equity Financing

    2.250.000,00 €

  • Common Equity

    6.910.680,00 €

Project Profit Forecast-Allocated to Equity Investor
  • Common Equity Investor (Scenario A: Land + Soft Costs)

    4,134,976.00€

  • Additional Capital Required (Scenario A)

    1,884,976,00 €

  • Profit Forecast (Scenario A) - Allocated to Common Equity Investor

    2.253.350,00 €

  • Total Projected Return (Scenario A)

    53.4%

  • Common Equity Investor (Scenario B: Land + Soft Costs + Hard Costs)

    6,910,680.00€

  • Profit Forecast (Scenario B) - Allocated to Common Equity Investor

    2.253.350,00 €

  • Total Projected Return (Scenario B)

    31.9%

III Project Cost Estimation

There's no major update compare to Q1 2024 project cost estimation.

Project Cost Estimation-Land Cost
  • Land Acquisition

    1,850,000.00 €

  • Taxes - IMT

    111,000.00 €

  • Total Land Cost

    1,961,000.00€

Project Cost Estimation Chart

Project Cost Estimation-Construction Cost Estimation
  • Total Land Cost

    1,961,000.00€

  • Architecture fee

    84,780.00 €

  • Permits & Fees

    120,000.00 €

  • Technical Projects

    246,632.00 €

  • Fiscalization & Consultants

    231,218.00 €

  • Project Development Fee

    1,156,088.00 €

  • Government Tax & HOA Subsidy

    27,454.00 €

  • Finance / Bank Costs - Other

    172,713.00 €

  • Utilities

    15,498.00 €

  • Insurance

    10,332.00 €

  • Marketing

    31,771.00 €

  • Accounting & Payroll

    20,664.00 €

  • Legal

    30,996.00 €

  • Other services - Overhead & Other

    25,830.00 €

  • Total Soft Costs

    2,173,976.00 €

  • Direct Costs

    12,076,410.00 €

  • Servicing/Furniture

    793,350.00 €

  • Hard Contingency

    1,139,284.00 €

  • Total Hard Costs

    14,009,044.00 €

  • Total Construction Costs (Soft + Hard)

    16,183,020.00 €

  • Total Land+Construction Cost (Soft + Hard)

    18,144,020.00 €

  • Construction Loan Interest

    1,082,549.00 €

  • Total Development Costs

    19,226,569.00 €

IV Typology & Sales Tracking

Typology&Sales Timeline Forecast
  • Typology

    Serviced Apartment

  • Average Size per Unit

    100 sqm

  • Average Price per Unit

    385,406.00 €

  • Average Price per Sqm

    3,849.00 €

  • Sales Timeline Estimation

  • 2024 Gross Sales Revenue(est.)

    1,040,595.00 €

  • 2025 Gross Sales Revenue(est.)

    1,387,460.00 €

  • 2026 Gross Sales Revenue(est.)

    20,696,286.00 €

  • Total Gross Sales Revenue(est.)

    23,124,341.00 €

Sales tracking
  • No information at this stage